There has been a lot of construction progress with the great spring weather. The exterior elevator is gone and the rest of precast brick panels was installed. The stainless steel column covers are about 98% complete and all grills are installed on the mechanical penthouse on the roof. The contractor has started on the foot bridge that will connect Pleasant St sidewalk to the foot bridge over Washington Avenue. The permanent electrical service was connected to the building to support the transition to more interior construction.
Drywall work and painting is complete on the fifth floor. Work is currently being done on the fifth floor flooring and finishes. The rest of the floors will follow consecutively.
The building is still on track to get LEED Gold Certification.
Fifth floor classroom